Idaho Power Provisioning
Idaho Power’s parent, IDACORP, has clear financial incentives to attract and serve these hyperscale loads, provided risks are contained. Large new customers like Meta, Gemstone, and Micron drive substantial capital investment – which can expand Idaho Power’s rate base and, in turn, its earningspuc.idaho.gov 1. In 2023, Idaho Power’s capital expenditures spiked to $734 million (from ~$315 million in 2021) as it began building out infrastructure for new load and clean energy projects. The utility negotiated a rate case settlement effective January 2024 that set its allowed Idaho return on equity around 9.4%, with an earnings sharing mechanism above ~9.5%. This means investments added to rate base can earn roughly ~9% returns until IDACORP hits that threshold. Company filings explicitly cite the Meta data center in Kuna and Micron’s Boise fab expansion as key drivers of load growth and the need for new resources.
For instance, in 2022 the IPUC approved a revised special contract with Micron (Idaho’s semiconductor manufacturer) so that Micron could purchase output from a new 40 MW solar farm under a 20-year PPA. That project came online in May 2023, enabling Micron to claim a portion of its huge power needs from renewable energy. The Micron deal, like Meta’s, included custom rate credits for the solar generation’s capacity value and required Micron to cover all costs. Idaho Power touts these arrangements as aligning large customers’ sustainability goals with the utility’s own 100% clean energy aspiration, while boosting sales: IDACORP has achieved 16 consecutive years of earnings growth, and it projects continued growth as it adds customers and invests in “energy storage, solar, and large transmission projects” to serve them.
At the same time, the utility and regulators recognize the concentration risk – if a data center or crypto load shuts down or radically changes, it could leave unused capacity or stranded costs. Idaho Power has addressed the most acute version of this risk by creating a special rate class for speculative “high-density loads” like cryptocurrency miners, who must pay marginal-cost energy prices and can be interrupted during peak season to protect the system. In contrast, established tech customers like Meta and Micron are given long-term contracts and are integrated into planning forecasts, mitigating risk through guarantees and dedicated resources. Overall, IDACORP’s strategy is to grow with these large loads – earning a return on facilitating their renewable projects and grid upgrades – without shifting costs to existing customers. The success of this approach now hinges on vigilant IPUC oversight and enforcement of contract terms, which is the focus of the next chapter on regulatory accountability.lf-puc.idaho.gov 2
Idaho Power’s plan to serve Meta’s new Kuna data center (code-named “Brisbie”) relies on a portfolio of dedicated solar generation and supporting infrastructure, all arranged under a special Energy Services Agreement (ESA)puc.idaho.gov 3. The utility negotiated long-term power purchase agreements (PPAs) for two large solar projects – Pleasant Valley Solar 1 (~200 MWₐc) and Pleasant Valley Solar 2 (~125 MWₐc) – exclusively to supply Meta’s loadpuc.idaho.gov 4puc.idaho.gov 5. The first 200 MW project came online in March–April 2025matrixrenewables.com 6pv-magazine-usa.com 7, and the second 125 MW phase is on track for early summer 2026. Idaho Power has also contracted the 320 MW Blacks Creek Solar farm (expected online December 2027) to meet Meta’s full future demand – with all energy from Blacks Creek dedicated to Meta under the Clean Energy Your Way programdocs.idahopower.com 8. To support reliability and peak loads, the utility is installing a 200 MW/800 MWh battery storage system at its Boise Bench substation by summer 2026. Idaho Power also constructed new delivery facilities – including a substation and high-voltage line extensions near Meta’s site in Kuna – funded upfront by Meta to ensure other customers bear none of the interconnection costslf-puc.idaho.gov 9. The provisioning map below summarizes how these pieces come together to serve Meta and the proposed Gemstone data center:
D1. Provisioning Map – Meta (Brisbie) and Gemstone Projects
|
Need |
Asset / Action |
Owner / Funding |
Timing |
Status |
Source |
|
Massive new energy supply for Meta (Phase 1) |
Pleasant Valley Solar 1 – 200 MW solar PPA (Ada County) |
rPlus/Matrix (IPP); PPA with Idaho Power (Meta as beneficiary) |
COD by Mar. 2025puc.idaho.gov 10matrixrenewables.com 11 |
Online. Project commissioned April 2025pv-magazine-usa.com 12 |
PPA approved Apr 2023 (20-year term)puc.idaho.gov 13. RECs assigned to Meta. |
|
Additional energy for Meta (Phase 2 growth) |
Pleasant Valley Solar 2 – 125 MW solar PPA (Ada County) |
rPlus/Matrix (IPP); PPA with Idaho Power (Meta as beneficiary) |
COD by May 31 2026puc.idaho.gov 14 (moved up from Dec 2026) |
Under construction. Tax equity secured; on track for summer 2026 operationpv-magazine-usa.com 15. |
PPA executed Dec 2023, IPUC approval pending in Case IPC-E-24-01puc.idaho.gov 16. Developer aligned schedule with Meta’s needs. |
|
Long-term full-load renewable supply for Meta |
Blacks Creek Solar – 320 MW solar PPA (Ada County) |
Developer TBD (Blacks Creek Energy Ctr.); 20-yr PPA with Idaho Power |
COD by Dec 2027docs.idahopower.com 17 |
Planned. PPA executed 2024 for Meta’s Clean Energy program. |
PPA approved 2024 (IPC-E-24-42) – output dedicated to Meta; RECs transferred to Meta. |
|
Peak capacity and grid support (Meta & region) |
Boise Bench Battery – 200 MW/800 MWh BESS (Ada County) |
Idaho Power (utility-owned, rate-based) |
Online by Summer 2026 (50 MW pending IPUC OK) |
In progress. 80 MW “Happy Valley” BESS by 2025; 200 MW Boise Bench by 2026. |
CPCN for 120 MW storage approved 2022idahopower.com 18; utility earning AFUDC during construction. |
|
Interconnection for Meta campus |
Kuna Substation & 138 kV line extensions (South Kuna) |
Idaho Power, funded by Meta via CIAC (Contribution in Aid) |
In service by 2024 Q4 (before energization) |
Complete. New substation and network upgrades energized to serve Metalf-puc.idaho.gov 19. |
Special Construction Agreement executed – Meta pays all costs “up to point of delivery” (no cost shift to other customers). |
|
Gemstone data center supply (initial phase) |
(TBD) – Potential new 100–200 MW renewable project under CEYW program |
Likely third-party IPP PPA (similar to Meta’s) |
Earliest ~2026–2027 (if approved in 2025) |
Proposed. No contract filed yet; load in planning stagedatacenterdynamics.com 20. |
Data needed. Gemstone’s developer (Diode Ventures) and Idaho Power expected to negotiate a special ESA; no public filings as of Sep 2025. |
|
Gemstone interconnection infrastructure |
New “Gemstone” substation & 138 kV line (Locust Grove Rd) |
Idaho Power, likely funded by Gemstone (CIAC or URD/TIF) |
Required by first phase energization (~2026) |
Planned. City zoning approval obtained; utility feasibility study donediodeventures.com 21boisedev.com 22. |
Gemstone to work with Idaho Power on “an improved substation” for the campus. Financing details not yet public – may involve CIAC or Kuna urban renewal funds. |
All three large solar resources for Meta are being developed and owned by independent power producers via 20-year PPAs, rather than utility-built generationpuc.idaho.gov 23docs.idahopower.com 24. These PPA assets are not included in Idaho Power’s rate base – instead, Meta will pay the full PPA costs through its special contract, and Meta receives the energy and renewable certificates from those projects. By contrast, the 200 MW battery storage project is a utility-owned asset that will enter Idaho Power’s regulated rate base, meaning the company can earn its allowed return (approximately 9–10% ROE) on that investment once it’s in servicepuc.idaho.gov 25. Likewise, any new transmission or substation built solely to serve the data centers is being treated as customer-funded infrastructure: Meta’s upfront CIAC payment offsets the capital cost so that it is not added to rate base or recovered from other customerslf-puc.idaho.gov 26. The asset ownership and cost treatment matrix below details who owns each major resource and how costs or returns are allocated:
D2. Asset Ownership & Rate Treatment
|
Resource / Facility |
Owner / Developer |
In Idaho Power Rate Base? |
Customer CIAC Funding? |
PPA Contract? |
AFUDC Accrued? |
Source / Notes |
|
Pleasant Valley Solar 1 (200 MW) |
rPlus Energies & Matrix (IPP) |
No. Third-party asset, sold to IP via PPApuc.idaho.gov 27 |
n/a (no utility capital) |
Yes – 20 yr PPA |
n/a (developer’s project, not utility CWIP) |
PPA approved Apr 2023; Meta is third-party beneficiary receiving energy & Green Tags (RECs). |
|
Pleasant Valley Solar 2 (125 MW) |
rPlus Energies (IPP) |
No. Not utility-owned (PPA)puc.idaho.gov 28 |
n/a |
Yes – 20 yr PPA. |
n/a |
PPA filed Jan 2024, approval expected 2024. Same developer as PV1; PPA cost passed entirely to Meta. |
|
Blacks Creek Solar (320 MW) |
Blacks Creek Energy Ctr. (IPP) |
No. PPA resource, not in rate basedocs.idahopower.com 29 |
n/a |
Yes – 20 yr PPA. |
n/a |
PPA executed 2024, expiring ~2047. All output dedicated to Meta under CEYW; RECs to Meta. |
|
Boise Bench BESS (200 MW battery) |
Idaho Power (utility asset) |
Yes. Will be added to rate base at COD |
No. System asset (for all customers) |
No (utility self-build) |
Yes. AFUDC capitalized during construction |
IPUC approved storage addition (120 MW initial)idahopower.com 30; 50 MW expansion awaiting approvaldocs.idahopower.com 31. Allowed ROE ~9.4% on rate-based investmentspuc.idaho.gov 32. |
|
Meta interconnection: Kuna substation & lines |
Idaho Power (built for Meta) |
No. CIAC offset removes from rate baself-puc.idaho.gov 33 |
Yes. Meta paid full construction cost |
No (network facility) |
n/a |
Special Facilities Construction Agreement ensures Meta funds “all costs… up to the point of delivery”. No return earned on CIAC-funded assets. |
|
Gemstone renewable supply (future) |
Likely IPP (to be determined) |
No (anticipated). Will use CEYW special contract like Meta |
Likely. Customer will fund dedicated resource costs |
Yes (expected). |
n/a |
Data needed. No contract yet; expected that Gemstone will not contribute to rate base if structured as PPA or customer-paid project. |
|
Gemstone interconnection facilities |
Idaho Power (planned) |
No (expected). If solely serving Gemstone, will be CIAC-funded |
Likely. To be funded via Gemstone or local URD/TIF |
No (network facility) |
n/a |
Gemstone to cover substation upgrade costs by agreementboisedev.com 34 (specific funding mechanism TBD). Idaho law may bar shifting these costs to other ratepayers. |
Critically, the special contracts and Clean Energy Your Way – Construction framework are designed to hold other ratepayers financially harmlesslf-puc.idaho.gov 35. Meta’s ESA contains numerous provisions to ensure “customer pays” means customer pays. For example, Meta must pay a Basic Load Capacity charge based on its expected peak demand, plus traditional demand and energy charges – this effectively serves as a minimum bill so that Meta contributes to fixed costs even if its usage is lower or its dedicated solar over-generates at timespuc.idaho.gov 36. The contract also requires robust credit support: Meta provided a parent company guaranty, and the ESA obligates Meta (or its guarantor) to cover any stranded costs if it exits earlydocs.idahopower.com 37puc.idaho.gov 38. This includes termination payments for remaining PPA obligations and any Idaho Power-owned upgrades – preventing those costs from being shifted to the general customer base. In addition, any excess energy** that Meta’s resources produce (e.g. surplus solar generation on a mild day) is not credited at full wholesale value – instead, the contract uses a discounted price (85% of Mid-C market, per IPUC guidance) so that Idaho Power’s other customers are insulated from market risk. The table below summarizes key risk areas and protections in place, based on the available evidence:
D3. “Customer Pays ⇒ Ratepayers Safe” Exposure Matrix
|
Risk Item |
Protection Required |
Proof in Place? |
Documented Source |
Exposure if Absent |
Next Action |
|
Network upgrade costs (substation, transmission) to serve new load |
Must be paid by the special-contract customer (CIAC), not rolled into rate base |
Yes. Meta’s Construction Agreement funds all interconnection facilities up to delivery point |
IPUC Order No. 35777 (Staff review) confirms no other ratepayers will bear these construction or O&M costs. |
If not fully funded by customer, existing customers would subsidize the expansion (higher rates to cover new substation/transmission). |
Verify similar CIAC terms in any Gemstone agreement; obtain CIAC payment records (e.g. IPUC compliance filing) once available. |
|
Resource delay or shortfall (customer’s dedicated project late or under-producing) – risk of high market purchases |
Customer must bear cost of any replacement energy (via special contract pricing or PCA mechanism) |
Partially. Contract includes pricing adjustments to shield others. IPUC requires reporting of Meta’s load vs generation annually. |
Staff imposed an 85% price cap on excess generation credits and other safeguards to ensure Idaho Power isn’t stuck with expensive imbalance costs. |
If protections failed, Idaho Power could incur costly market purchases to serve Meta, potentially seeking recovery from all customers. |
Monitor annual filings of Brisbie load/gen balance; ensure any shortfall costs are allocated to Meta through the Power Cost Adjustment. |
|
Load fluctuation or usage below expectations – risk of unrecovered fixed costs |
Minimum billing demand or fixed charge to cover capacity costs regardless of usage |
Yes. Special Schedule 33 includes a Basic Load Capacity charge (based on 1,000 kW min. and Meta’s two highest demand months)puc.idaho.gov 39 plus standard demand charges. |
Tariff Schedule 33 (Meta ESA rate) sets monthly charges that do not fall below a base level even if energy usage drops. |
Without a minimum bill, other customers would have to pick up Meta’s share of fixed generation and grid costs during low-usage periods. |
Audit Meta’s billing to confirm minimum charges are applied; for future contracts, ensure similar or stronger provisions (e.g. contract demand commitments). |
|
Customer default or exit before end of term – risk of stranded PPA or assets |
Binding parent guaranty and termination payments covering all remaining costs |
Yes. ESA requires parent guarantee and full stranded cost recoverydocs.idahopower.com 40; PPA itself includes parent guaranty by Metapuc.idaho.gov 41. |
IPUC orders (and now Schedule 62 rules) mandate a financial guarantee for the life of the projectdocs.idahopower.com 42. Meta’s guaranty would fund any unpaid costs if Meta ceased operations. |
If no guarantee, Idaho Power could be left with a 20-year solar PPA or idle infrastructure and no revenue – costs would shift to general rates. |
Obtain and review the guaranty agreement (confidential exhibit) to verify its sufficiency; for Gemstone, demand equivalent credit support (letter of credit or guarantee from Black & Veatch/Diode’s backers). |
|
Stranded asset “roll-in” (utility seeks to rate-base assets if customer leaves) |
Explicit prohibition – assets must be removed from rate base or otherwise compensated by customer |
Likely. The ESA structure and guaranty effectively prevent roll-inlf-puc.idaho.gov 43 (no explicit roll-in clause seen). |
Staff emphasized that without full cost recovery from Brisbie, they “would be hard-pressed to find public interest” in approval. The approved contract assigns responsibility to Brisbie, not customers, for dedicated resource costs. |
If a stranded asset were rolled into general rates, all customers would pay for a project that was meant to be exclusive – violating “no harm” intent. |
Ensure IPUC final orders and the contract explicitly bar cost socialization. If any ambiguity, address in next regulatory proceeding (e.g. a declaratory ruling or contract addendum). |
|
Urban Renewal/TIF reliance (if public financing used for infrastructure expecting tax increment from data center) |
Sufficient taxable value must materialize; backup plan if project delayed or de-scoped |
Unclear. Kuna created an Urban Renewal District for Meta’s site, expecting Meta’s property taxes to repay bondsblog.idahoreports.idahoptv.org 44boisedev.com 45. Legislative attempts to exclude the data center from the URD indicate this risk was recognized. |
Idaho lawmakers debated a 2023 bill to prevent including Meta’s project in a URD, citing concerns that diverting such a large tax base could “hurt… Kuna’s East Urban Renewal” if assumptions failblog.idahoreports.idahoptv.org 46boisedev.com 47. The bill did not passblog.idahoreports.idahoptv.org 48, so the URD stands, placing local infrastructure funding on Meta’s tax contributions. |
If Meta’s build-out is delayed or downsized (Meta paused some projects in 2022datacenterdynamics.com 49), the URD could face revenue shortfalls. Kuna’s taxpayers or services would shoulder the gap, though this doesn’t directly raise electric rates, it heightens community financial exposure. |
Review Kuna URD plan and bond official statements for contingency provisions. If shortfall risk is high, local officials may need to renegotiate timelines or secure guarantees from Meta for tax payments. |
Under the Clean Energy Your Way – Construction program, Meta and similar large customers effectively get to claim “100% renewable” operations while Idaho Power ensures the grid reliably meets their needsidahopower.com 50lf-puc.idaho.gov 51. Meta’s special contract was explicitly “modeled after” this programpuc.idaho.gov 52. The mechanics are as follows: the customer works with Idaho Power to add new renewable generation to the system (through a PPA or a utility-built project), sized up to at most 110% of the customer’s annual load so as not to over-generate excessivelydocs.idahopower.com 53. A separate Renewable Construction Agreement governs the arrangement, detailing the REF Cost (the full cost of the dedicated renewable facility) and the REF Credit (the measurable benefit that resource provides to Idaho Power’s system). On each monthly bill, the participant continues to pay all normal tariff charges for power delivery and backup service, but they also pay the REF Cost of their dedicated resource and in return receive the REF Credit for its output. In practice, this means the customer bears all costs of procuring and integrating their renewable supply – and in exchange they receive the renewable energy certificates (RECs) and environmental attributes from that project, plus credit for its energy and capacity contributionpuc.idaho.gov 54. Idaho Power essentially acts as the facilitator: integrating the new resource into its grid and “balancing” any differences between when the resource produces and when the customer uses power. If the customer’s solar farm produces more than the customer’s usage in a given hour, that Excess Generation flows to the grid – the customer is credited at a discounted rate as noted (so other customers benefit from the surplus energy value). If the dedicated resource produces less or is offline, the customer simply draws additional power from Idaho Power’s system at standard rates, like any other user. Crucially, the program requires financial guarantees to protect everyone else: any participant must provide a security guarantee covering stranded costs if they default or relocate, so that remaining ratepayers are never left holding the bag for a abandoned renewable project. The table below outlines the key elements of the CEYW–Construction offering as implemented:
D4. Clean Energy Your Way – Construction Program Mechanics
|
Program Element |
Key Provisions (Rules) |
Who Pays? |
Who Owns Resource? |
RECs & Attributes |
Rate/Billing Treatment |
Sources |
|
Eligibility & Scope |
Schedule 62 Construction option open to large customers (>1 MW, typically Schedule 19 special contract) seeking new dedicated renewables. Project size ≤ 110% of customer’s annual usage (to prevent excessive surplus). |
Customer (participant) initiates request and must meet size and credit criteria. |
Resource can be third-party (PPA) or utility-built – “generation type, size, timing, location, and ownership” are case-by-case, subject to IPUC approval to keep others harmless. |
All new – must be new-build renewable (solar, wind, etc.) not already in Idaho Power’s portfolio. Existing PURPA/QF projects cannot be used. |
Not a standard tariff supply; each project requires a Renewable Construction Agreement between customer and Idaho Power. |
|
|
Financing of Project |
Customer is responsible for 100% of project costs (“REF Cost”) – via PPA price or cost-of-service charge if utility-owned. Idaho Power may facilitate procurement but will not invest without full cost recovery from the customer. |
Customer pays all capital and operating costs of the renewable facility (either through PPA payments or a negotiated cost reimbursement)lf-puc.idaho.gov 55docs.idahopower.com 56. |
If PPA: third-party developer finances, owns, and sells energy to Idaho Power for the customer’s benefitpuc.idaho.gov 57. If utility-built: Idaho Power owns the asset but the customer’s payments cover its revenue requirement (so no net cost to others). |
Customer effectively finances via contract: e.g. Meta’s PPA rates include building the plantmatrixrenewables.com 58. Idaho Power’s role is to ensure the project is built and integrated, using standard procurement if neededlf-puc.idaho.gov 59puc.idaho.gov 60. |
IPUC authorizes Idaho Power to procure new resources for CEYW customers outside normal IRP/RFP processlf-puc.idaho.gov 61puc.idaho.gov 62. No cost recovery from non-participants – costs are isolated to the special contract (tracked via separate Schedule 33/62 accounts). |
|
|
RECs (Renewable Certificates) |
All RECs from the dedicated resource go to the customer to fulfill their sustainability goalslf-puc.idaho.gov 63puc.idaho.gov 64. The customer may also buy additional RECs via the CEYW–Flexible option if needed (for load growth or interim needs)idahopower.com 65docs.idahopower.com 66. |
Customer pays any and all costs to secure those RECs (since they fund the resource). Idaho Power forfeits any claim on those RECs – it delivers them to the customer or retires them on the customer’s behalfpuc.idaho.gov 67docs.idahopower.com 68. |
RECs are created by the project owner (or tracked in WREGIS) but contractually assigned to Idaho Power for delivery to the customerpuc.idaho.gov 69docs.idahopower.com 70. |
The customer can claim to be powered 100% by new renewable energy once it receives these RECsidahopower.com 71. Meanwhile, Idaho Power removes those RECs from its portfolio (so they are not counted toward the utility’s own green goals)docs.idahopower.com 72lf-puc.idaho.gov 73. |
Example: Meta’s 200 MW solar PPA explicitly names Meta as the third-party beneficiary receiving all energy and environmental attributes (Green Tags) from the projectpuc.idaho.gov 74. |
|
|
Billing & Credits |
Participant continues to pay regular tariff charges for base service (customer, demand, energy charges per Schedule 19 or equivalent)puc.idaho.gov 75. On top of that, Schedule 62 adds: (1) a charge for the REF Cost of the new resource, and (2) a REF Credit for the resource’s output and capacity value to the systemdocs.idahopower.com 76. These elements are defined in the Construction Agreement and approved by IPUC to ensure fairness. |
Customer pays net of two streams: they pay the full cost of their resource, but they get credited what that resource is worth to Idaho Power’s system (avoided energy/capacity cost). The customer also pays all normal delivery costs. |
Idaho Power initially pays the PPA or incurs project costs, then bills the customer for them (cost pass-through)puc.idaho.gov 77lf-puc.idaho.gov 78. Idaho Power provides a credit on the bill for avoided purchases – e.g. if the resource generated 10 GWh that month, the customer gets credit at the prevailing avoided cost or market rate minus adjustment. |
Net effect: the customer’s bill reflects their usage minus their resource’s output. If in an hour the resource equals the load, the customer effectively pays just the fixed grid charges. If the resource under-produces, the customer pays Idaho Power for supplemental energy. If it over-produces, the customer still pays the PPA cost but is credited a portion of market value for the surplus. All this is settled on the bill each month. |
Meta’s Schedule 33, for example, lists standard energy and demand rates and separate line items for “Embedded Energy Fixed Cost” credits – reflecting that Meta’s solar reduces Idaho Power’s need to run other resourcespuc.idaho.gov 79. Excess generation is credited at 85% of market to account for Idaho Power’s resale risklf-puc.idaho.gov 80. Any capacity contribution from Meta’s projects is accounted for via credits only when the system is capacity-deficient. |
|
|
Term & Exit Conditions |
Negotiated contract term, typically aligned with project life or PPA (e.g. 20 years)puc.idaho.gov 81. Financial guaranty required: customer (or its parent) must guarantee to cover all stranded costs if the customer closes or leaves before term endsdocs.idahopower.com 82. The contract also stipulates any performance guarantees or liquidated damages for the resource (e.g. if project output is below expected)puc.idaho.gov 83lf-puc.idaho.gov 84. |
Customer is on the hook for the duration. If they terminate early, they pay out any remaining costs (such as buying out the PPA or reimbursing Idaho Power for undepreciated investments)docs.idahopower.com 85. Idaho Power’s other customers pay $0 of those stranded costs. |
Ownership of the resource in case of early exit would depend on contract: with a PPA, Idaho Power could redirect the energy to general supply (but Meta or its guarantor would still pay the above-market costs, if any, through termination fees). With utility-owned, Idaho Power might retain the asset but the customer’s payments (or guaranty) would continue to cover its revenue requirement. |
The customer does not have unilateral “off-ramp” without cost – any exit triggers contractual damages to make Idaho Power whole. If the customer simply reduces operations, the minimum bill provisions ensure they still contribute to fixed costspuc.idaho.gov 86lf-puc.idaho.gov 87. |
The IPUC required that “the Renewable Construction Agreement must include a Customer financial guarantee to cover stranded ... costs in the event of Customer default, dissolution, and/or relocation.”docs.idahopower.com 88. In Meta’s case, Meta’s parent guarantee satisfies this. Micron’s 40 MW solar contract and other CEYW deals have similar guarantees and minimum term commitmentspuc.idaho.gov 89. |
|
|
Curtailment & Reliability |
Unless specified (e.g. separate interruptible rate), CEYW customers receive firm service like any other large customer. They are not granted priority over other firm loads – nor are they subject to special curtailments except as agreed (Meta’s contract does not indicate any interruptibility; by contrast, crypto-mining loads under Schedule 20 are interruptible by summer grid need). |
Customer pays for reliable service and expects the same reliability as others. Idaho Power maintains reserves and dispatchable resources to cover all firm customers, including Meta/Gemstone, even when renewable output fluctuatesidahopower.com 90. The customer’s rates (demand charges, etc.) ensure they contribute to those reliability costs. |
Idaho Power retains control over the grid. If an emergency or capacity shortfall occurs, Meta could be curtailed under system-wide emergency plans on an equal footing with other large industrial customers. The special contract does not exempt them from outages or rotating blackouts if it came to that. |
The dedicated resource can be curtailed by Idaho Power for reliability if needed (the PPA allows curtailment under grid emergency, typically). The customer bears the production risk – no compensation if their resource is curtailed for system reliability beyond what the contract outlines. Meanwhile, they’d draw power from the grid (and pay for it) if their resource is offline. |
In general, Idaho Power required potentially unstable high-density loads (e.g. crypto miners) to be interruptible and pay a premium for energypuc.idaho.gov 91. By contrast, Meta and Micron are treated as standard large customers with long-term commitments, so no routine curtailment clause beyond force majeure. Their contribution to peak demand is accounted for in planning (with new resources and the BESS) to preserve overall reliabilitydocs.idahopower.com 92docs.idahopower.com 93. |
|
puc.idaho.gov 94 IDACORP 2023 Annual Report
puc.idaho.gov 95 puc.idaho.gov
puc.idaho.gov 96 Application (00326430).DOCX
matrixrenewables.com 97 Matrix Renewables and rPlus Energies celebrate the commissioning of Pleasant Valley Solar 1 - Matrix Renewables
pv-magazine-usa.com 98 Pleasant Valley Solar 2 financing clears way for data centers and high-tech manufacturing in Idaho – pv magazine USA
docs.idahopower.com 99 2025 Integrated Resource Plan
idahopower.com 101 Idaho Power Announces Plans for State’s First Large-scale Battery Storage Projects - Idaho Power
datacenterdynamics.com 102 Diode Ventures plans 620-acre data center park in Kuna, Idaho - DCD
diodeventures.com 103 Gemstone Project Updates - Diode Ventures
boisedev.com 104 Data center could bring multi-million deals to Kuna
puc.idaho.gov 105 Microsoft Word - Brisbie - Application - 12-22-21 (002).docx
docs.idahopower.com 106 Schedule 62 - Clean Energy Your Way - Optional
blog.idahoreports.idahoptv.org 107 Bill passed to exclude data center from urban renewal area
boisedev.com 108 Kuna speaks out against bill removing Meta data center ... - BoiseDev
blog.idahoreports.idahoptv.org 109 Data center urban renewal bill dies in committee - Idaho Reports
idahopower.com 110 Idaho Power Requests Special Contract with Enterprise Data Center - Idaho Power
docs.idahopower.com 111 RFP Resource Update
Sources
Unique citations: 10 · In-text mentions: 111